| TITLE | Construction Advisory/Web Page |
|
| PROJECT CODE | 6b-2B |
|
| COMMITTEE | Travel Information Services |
|
| YEAR FUNDED | Year 6 - FY 1998 |
|
| Year 6 Budget: | $48,000 |
|
| STATUS | Completed |
|
| DESCRIPTION |
Construction Advisory: This is an ongoing effort resulting from early traveler information and incident management activities. It was developed to provide member agencies with construction information in neighboring jurisdictions.
Web Page: These funds covered operations and maintenance of the Coalition's first web site. The web site provided basic traveler information, reports, membership information and current news. |
|
| CONTACTS |
Procurement Agency: Connecticut DOT
Project Contact: Patty Reich, Transcore |
| TITLE | Construction Advisory/Web Page |
|
| PROJECT CODE | 6b-2B |
|
PROJECT DATES
| Project Start: |
|
| Expected Completion: |
|
|
|
| Year 6 Budget: | $48,000 |
|
| OBJECTIVES |
To provide information to the traveling public and to member agencies. |
|
| SCOPE |
No data.
|
|
| REPORTS |
| Report Name |
Report
|
| Construction Advisory/Web Page - deliverables |
View  |
|
|
| END OF PROJECT SUMMARY |
Construction Advisory: The construction advisory is produced every two weeks throughout most of the year (every four weeks in the winter months) and details all lane closures on major roadways throughout the Corridor. It is distributed by mail, fax and e-mail to traffic operations centers, member agencies and private partners. It is also posted on the Coalition's web site.
Web Page: The operations and maintenance of the Coalition's web site is an ongoing effort and includes the addition of documents, photos and links. The web site serves as a source of Coalition historical information, planned events and traveler information. |
|
| ACTIONS |
Construction Advisory: Occasional surveys have been conducted of the recipients to insure that the information as presented is useful and timely.
Web Page: The Coalition's web site will continue to expand and evolve as a clearinghouse for all Coalition meetings, historical documents, notices, organizational items, etc. as the Coalition membership and interest grows. |
|
| FINAL PROJECT EXPENDITURES |
FY1998: $48,000
Amount Spent: $45,140
Year 6 Travelers |
|
|
|
|
|